When does the Future Homes Standard actually apply?

Part L and the Future Homes Standard · 2 min read

The dates, plainly:

DateWhat happens
24 March 2026The Future Homes Standard was laid and published (Approved Document L Volume 1, 2026 edition, England)
4 March 2027The parallel Welsh regulations come into force
24 March 2027FHS in force in England for building work that is not a higher-risk building
24 September 2027FHS in force for higher-risk buildings
24 March 2028The transitional cliff: dwellings not commenced by this date lose transitional protection

The transitional rules — where plots get caught

A dwelling can complete under Part L 2021 only if both of these hold:

  1. its building notice, initial notice or full-plans application was submitted before 24 March 2027, and
  2. construction of that dwelling has commenced by 24 March 2028.

Two sharp edges to note:

  • Protection is per individual dwelling, not per site. Submitting for a whole development does not shelter plots that have not started — each dwelling must itself commence in time.
  • 'Commenced' has been tightened. Under Regulation 46A it now requires the ground-floor level structure to be in place — foundations alone no longer qualify.

The older transitional arrangements that let some large sites keep building to earlier standards are also sunsetted: those dwellings must likewise start by 24 March 2028.

Whichever side of the line a plot falls, the photographic evidence duty applies — it has been law since June 2022 (the current requirement) and the 2026 edition extends it (what changes).

Verified against primary sources 13 July 2026.

Did this article help?

Still need help? Ask a question